Project Management Professional (PMP) Exam Practice – Question1573
As project manager, you have assembled the team to prepare a comprehensive list of project risks. Which one of the following documents would be the most helpful in this process?
A. OBS B. WBS C. RBS D. CBS
Correct Answer: C
Explanation:
Explanation:
The risk breakdown structure (RBS) helps to provide framework for ensuring a comprehensive process of systematically identified risks. It is a hierarchically organized depiction of the identified risks by risk categories.