Project Management Professional (PMP) Exam Practice – Question1576

A workaround is______________


A.
An unplanned response to a negative risk event
B. A plan of action to follow when something unexpected occurs
C. A specific response to certain types of risk as described in the risk management plan
D. A proactive, planned method of responding to risks

Correct Answer: A

Explanation:

Explanation:
Used in control risks, a workaround is a response to a threat that has occurred for which a prior response had not been planned or was not effective.