Project Management Professional (PMP) Exam Practice – Question1578

In the below path convergence example, if the odds of completing activities 1, 2, and 3 on time are 50 percent, 50 percent, and 50 percent, what are the chances of starting activity 4 on day 6?



A.
10 percent
B. 13 percent
C. 40 percent
D. 50 percent

Correct Answer: B

Explanation:

Explanation:
Probability (starting activity 4 on day 6)=(0.5)3
=0.125 or 13%