Each one of the following statements about risk avoidance is true EXCEPT that it______________


A.
Focuses on changing the project management plan to eliminate entirely the threat
B. Isolates the project's objectives from the risk's impact
C. Accepts the consequences of the risk event should it occur
D. Changes the project objective that is in jeopardy

Correct Answer: C

Explanation:

Explanation:
Accepting the consequences of the risk event is categorized as risk acceptance. With this risk response approach, the project team takes no action to reduce the probability of the risk’s occurring.