Project Management Professional (PMP) Exam Practice – Question1584

Your project team has identified all the risks on the project and has categorized them as high, medium, and low. The "low" risks are placed on which one of the following for monitoring?


A.
Threat list
B. Low risk list
C. Watch list
D. Low impact list

Correct Answer: C

Explanation:

Explanation:
Even low-priority risks must be monitored. A watch list is used to ensure such risks are tracked for continued monitoring.