A recent earned value analysis shows that your project is 20 percent complete, the CPI is 0.67, and the SPI is 0.87. In this situation, you should______________
A. Perform additional resource planning, add resources, and use overtime as needed to accomplish the same amount of budgeted work
B. Rebaseline the schedule, then use Monte Carlo analysis
C. Conduct a risk response audit to help control risk
D. Forecast potential deviation of the project at completion from cost and schedule targets
A. Perform additional resource planning, add resources, and use overtime as needed to accomplish the same amount of budgeted work
B. Rebaseline the schedule, then use Monte Carlo analysis
C. Conduct a risk response audit to help control risk
D. Forecast potential deviation of the project at completion from cost and schedule targets