Project Management Professional (PMP) Exam Practice – Question1591

Risk score measures the______________


A.
Variability of the estimate
B. Product of the probability and impact of the risk
C. Range of schedule and cost outcomes
D. Reduced monetary value of the risk event

Correct Answer: B

Explanation:

Explanation:
The risk score provides a convenient way to compare risks because comparing impacts or probabilities alone is meaningless. It helps guide risk responses.