Which of the following is an example of recommended corrective action in risk management?
A. Conducting a risk audit
B. Engaging in additional risk response planning
C. Performing the contingency plan
D. Conducting a risk review
A. Conducting a risk audit
B. Engaging in additional risk response planning
C. Performing the contingency plan
D. Conducting a risk review