Project Management Professional (PMP) Exam Practice – Question1592

Which of the following is an example of recommended corrective action in risk management?


A.
Conducting a risk audit
B. Engaging in additional risk response planning
C. Performing the contingency plan
D. Conducting a risk review

Correct Answer: C

Explanation:

Explanation:
Corrective action in risk management is the process of making changes to bring expected performance in line with the risk management plan. Such action consists of performing either the planned risk response, such as implementing contingency plans, or a
workaround.