Project Management Professional (PMP) Exam Practice – Question1594

Your project is using complex, unproven technology. Your team conducted a brainstorming session to identify risks. Poor allocation of project resources was the number one risk. This risk was placed on the risk register, which included at this point
a______________


A.
Watch list
B. Potential risk response
C. Known unknown
D. List of other risks requiring additional analysis

Correct Answer: B

Explanation:

Explanation:
The risk register is prepared first in the identify risks process. It contains a list of identified risks in as much detail as possible and a list of potential responses when they are identifiable at this time.