Project Management Professional (PMP) Exam Practice – Question1596

Risk mitigation involves______________


A.
Using performance and payment bonds
B. Eliminating a specific threat by eliminating the cause

C. Avoiding the schedule risk inherent in the project
D. Reducing the probability and/or impact of an adverse risk event to an acceptable threshold

Correct Answer: D

Explanation:

Explanation:
It is often more effective to take early action to reduce probability and/or impact of a risk occurring on a project than attempting to repair the damage after the risk has occurred.