On a typical project, when are risks highest and impacts (amount at stake) lowest?
A. During the concept phase
B. At or near completion of the project
C. During the implementation phase
D. When the project manager is replaced
A. During the concept phase
B. At or near completion of the project
C. During the implementation phase
D. When the project manager is replaced