Project Management Professional (PMP) Exam Practice – Question1598

Two key inputs to the perform quantitative risk analysis process are the______________


A.
WBS and milestone list
B. Scope management plan and process improvement plan
C. Schedule management plan and cost management plan
D. Procurement management plan and quality baseline

Correct Answer: C

Explanation:

Explanation:
The cost and schedule of a project are two areas significantly affected by risk occurrences. Information on these two areas, because of their quantitative nature, provides excellent input to the perform quantification risk process to help determine overall impact and
to provide guidelines as managing risk reserves.