Project Management Professional (PMP) Exam Practice – Question1599

The highest risk impact generally occurs during which one of the following project life-cycle phases?


A.
Concept and planning
B. Planning and implementation
C. Implementation and closeout
D. Concept and closeout

Correct Answer: C

Explanation:

Explanation:
Opportunity and risk generally remain high during the concept and planning phases. However, the amount at stake remains low because of the relatively low level of investment up to that point. During project implementation and closeout, however, risk falls to
lower levels as remaining unknowns are translated into knowns. At the same time, the amount at stake rises steadily as the necessary resources are invested to complete the project.