Which one of the following statements best characterizes an activity cost or duration estimate developed with a limited amount of information?
A. It should be part of the planning for the needed management reserve.
B. It is an input to identify risks.
C. It is an output from identify risks.
D. It must be factored into the list of prioritized project risks.
A. It should be part of the planning for the needed management reserve.
B. It is an input to identify risks.
C. It is an output from identify risks.
D. It must be factored into the list of prioritized project risks.