Accurate and unbiased data are essential for perform qualitative risk analysis. Which one of the following should you use to examine the extent of understanding of project risk?


A.
Data quality assessment
B. Project assumptions testing
C. Sensitivity analysis
D. Influence diagrams

Correct Answer: A

Explanation:

Explanation:
Perform qualitative risk analysis requires accurate and unbiased data. The use of low-quality data may result in a qualitative risk analysis that is of little use to the project manager regarding understanding of the risk, data available about the risk, data quality, and
data reliability and integrity.