Project Management Professional (PMP) Exam Practice – Question1603

Assigning more talented resources to the project to reduce time to completion or to provide better quality than originally planned are examples of which one of the following strategies?


A.
Enhance
B. Exploit
C. Share
D. Contingent response

Correct Answer: B

Explanation:

Explanation:
Although it might have a negative connotation, exploitation is a strategy used for risks with positive impacts where the organization wants to ensure that the opportunity is realized.