Contingency planning involves______________
A. Defining the steps to be taken if an identified risk event should occur
B. Establishing a management reserve to cover unplanned expenditures
C. Preparing a stand-alone document that is separate from the overall project plan
D. Determining needed adjustments to make during the implementation phase of a project
A. Defining the steps to be taken if an identified risk event should occur
B. Establishing a management reserve to cover unplanned expenditures
C. Preparing a stand-alone document that is separate from the overall project plan
D. Determining needed adjustments to make during the implementation phase of a project