You are the project manager for the construction of an incinerator to burn refuse. Local residents and environmental groups are opposed to this project. Management agrees to move this project to a different location. This is an example of which one of the
following risk responses?
A. Passive acceptance
B. Active acceptance
C. Mitigation
D. Avoidance
following risk responses?
A. Passive acceptance
B. Active acceptance
C. Mitigation