Project Management Professional (PMP) Exam Practice – Question1615

Significant differences between the seller's price and your independent estimate may indicate all the following EXCEPT the______________


A.
SOW was not adequate
B. Seller misunderstood the SOW
C. Sellers failed to respond
D. Project team chose the wrong contract type

Correct Answer: D

Explanation:

Explanation:
The contract type is typically dictated by the procurement SOW and chosen by the contracting officer. Independent estimates are a tool and technique in conduct procurements.