Project Management Professional (PMP) Exam Practice – Question1616

You are a contractor for a state agency. Your company recently completed a water resource management project for the state and received payment on its final invoice today. A procurement audit has been conducted. Formal notification that the contract has been
closed should be provided to your company by the______________


A.
State's project manager
B. Person responsible for procurement administration
C. Project control officer
D. Project sponsor or owner

Correct Answer: B

Explanation:

Explanation:
The person responsible for procurement administration should provide, in writing, formal notification that the contract has been completed. Requirements for formal acceptance and closeout should be defined in the contract.