Because you are working under a firm-fixed-price contract, management wants you to submit the final invoice and close out the contract as soon as possible. Before final payment on the contract can be authorized, you must______________
A. Prepare a contract completion statement
B. Audit the procurement process
C. Update and archive contract records
D. Settle subcontracts
A. Prepare a contract completion statement
B. Audit the procurement process
C. Update and archive contract records
D. Settle subcontracts