Project Management Professional (PMP) Exam Practice – Question1622

As you prepare to close out contracts on your project, you should review all the following types of documentation EXCEPT the______________


A.
Contract document for the contract being closed
B. Procurement audit report
C. Invoice and payment records
D. Seller performance reports

Correct Answer: B

Explanation:

Explanation:
In most organizations, a procurement audit is conducted after the contract has been closed. Therefore, the project manager would not have a procurement audit report to review. Contract document for the contract being closed, invoice and payment records, and
seller performance reports are examples of the documents that should be available to the project manager and should be reviewed at closeout.