Project Management Professional (PMP) Exam Practice – Question1625

Requirements for formal contract acceptance and closure usually are defined in the______________


A.
Proposal
B. Statement of work
C. Contract terms and conditions
D. Procurement audit report

Correct Answer: C

Explanation:

Explanation:
The contract terms and conditions typically describe the procedure the buyer will employ to close the contract.