Project Management Professional (PMP) Exam Practice – Question1626

You plan to award a contract to provide project management training for your company. You decide it is important that any prospective contractor have an association with a major university that awards master's certificates in project management. This is an
example of______________


A.
Setting up an independent evaluation
B. Preparing requirements for your statement of work
C. Establishing a weighting system
D. Establishing source selection criteria

Correct Answer: D

Explanation:

Explanation:
The selection criteria are typically included in procurement documents and are then used to rate or score proposals.