You plan to award a contract to provide project management training for your company. You decide it is important that any prospective contractor have an association with a major university that awards master's certificates in project management. This is an
example of______________
A. Setting up an independent evaluation
B. Preparing requirements for your statement of work
C. Establishing a weighting system
D. Establishing source selection criteria
example of______________
A. Setting up an independent evaluation
B. Preparing requirements for your statement of work
C. Establishing a weighting system
D. Establishing source selection criteria