Project Management Professional (PMP) Exam Practice – Question1629

You are responsible for ensuring that your seller's performance meets contractual requirements. For effective contract control, you should______________


A.
Hold a bidders' conference
B. Establish the appropriate contract type
C. Implement the contract change control system
D. Develop a statement of work

Correct Answer: C

Explanation:

Explanation:
Contract change control entails ensuring that contract changes are properly approved and that everyone who needs to know is made aware of such changes.