Project Management Professional (PMP) Exam Practice – Question1634

As project manager, you need a relatively fast and informal method addressing disagreements with contractors. One such method is to submit the issue in question to an impartial third party for resolution. This process is known as______________


A.
Alternative dispute resolution
B. Problem processing
C. Steering resolution
D. Mediation litigation

Correct Answer: A

Explanation:

Explanation:
Alternative dispute resolution, or dispute resolution, is a relatively informal way to address differences of opinion on contracts. Its purpose is to address such issues without having to seek formal legal redress through the courts.