As project manager, you need a relatively fast and informal method addressing disagreements with contractors. One such method is to submit the issue in question to an impartial third party for resolution. This process is known as______________
A. Alternative dispute resolution
B. Problem processing
C. Steering resolution
D. Mediation litigation
A. Alternative dispute resolution
B. Problem processing
C. Steering resolution
D. Mediation litigation