Project Management Professional (PMP) Exam Practice – Question1638

Requirements for formal deliverable acceptance are defined in the______________


A.
Contract
B. Procurement management plan
C. Overall project management plan
D. Specifications

Correct Answer: A

Explanation:

Explanation:
Two important components of any contract include what the buyer wants to buy and how the buyer defines acceptance of the products or services delivered. For contract closure to occur, deliverable acceptance must be completed.