All of the following are examples of good control procurement skills that project managers need to exercise EXCEPT______________


A.
Approving invoices as the work is completed
B. Supervising the work to be done under the terms of the contract
C. Developing contract clauses
D. Preparing and processing change requests

Correct Answer: C

Explanation:

Explanation:
First, developing contract clauses is done during contract formation, not control procurements, which begins at contract signing. Second, contract specialists and attorneys______________given their legal expertise______________are typically the individuals