Project Management Professional (PMP) Exam Practice – Question1644

During contract negotiations on large contracts, the negotiation process focuses on many key issues, with price being one of them. Separate negotiations can be made on price, quantity, quality, and timing, which can significantly lengthen the process. The
negotiation process can be shortened, however, provided that______________


A.
Planning is done for negotiations
B. Expertise of the project management staff in the procurement process is at a high level
C. A request for proposal is used rather than a request for quotation
D. There is integrity in the relationship and prior history with the vendor

Correct Answer: D

Explanation:

Explanation:
When people know and trust one another, and in particular have worked with each other before, the negotiation process can be significantly shortened. Three major factors of negotiation should be followed: compromise ability, adaptability, and good faith.