Project Management Professional (PMP) Exam Practice – Question1651

Analyzing stakeholders is a part of the identify stakeholders process. Common approaches for analyzing stakeholders in a qualitative manner includes all the following two-axis grids, EXCEPT______________


A.
Comparing power and influence
B. Comparing power and interest
C. Comparing influence and location
D. Comparing influence and impact

Correct Answer: C

Explanation:

Explanation:
Identifying and analyzing the stakeholders helps to classify them better for developing a strategy to help manage them and their expectations throughout the project. The most common comparison elements are: power, influence, interest, and impact. The location
of the person may have an impact on one of the other measures, but it is not easily quantifiable on a low, medium, high, type scale.