Project Management Professional (PMP) Exam Practice – Question1652

You are responsible for a project in your organization that has multiple internal customers.
Because many people in your organization are interested in this project, you decide to prepare a stakeholder management strategy. Before preparing this strategy, you should______________


A.
Conduct a stakeholder analysis to assess information needs
B. Determine a production schedule to show when each stakeholder needs each type of information produced
C. Determine the potential impact that each stakeholder may generate
D. Prioritize each stakeholder's level of interest and influence

Correct Answer: A

Explanation:

Explanation:
Stakeholder analysis is used to analyze the information needs of the stakeholders and to determine the sources for meeting those needs. It helps to determine whose interests should be taken into account throughout the project.