Project Management Professional (PMP) Exam Practice – Question1653

Recognizing the importance of preparing a stakeholder management plan, you met with your team to obtain their buy in and to discuss it. You explained the key benefit of plan stakeholder management is to______________


A.
Determine appropriate strategies for a continual focus on identifying stakeholders throughout the life cycle
B. Provide a clear plan that is actionable to interact with stakeholders to support the project's interests
C. Develop appropriate management strategies to effectively engage stakeholders
D. Plan a series of meetings to ensure stakeholders remain interested and to address their concerns

Correct Answer: B

Explanation:

Explanation:
While the plan stakeholder management process develops appropriate management strategies to effectively engage the stakeholders during the project life cycle, the key benefit of this process is to have a plan that is clear and actionable to interact with them to
support the project’s interests.