Stakeholders often have issues, and you have asked each of your team members to document them. At each team meeting, you and your team discuss them and determine appropriate responses. You have a project issue log, which is______________


A.
Part of the project's lessons learned
B. Added to the stakeholder register to show which stakeholder raised it
C. An output from the manage stakeholder engagement process
D. An output from the control stakeholder engagement process

Correct Answer: C

Explanation:

Explanation:
Issues logs are an output of this process, as issues are expected in this process. The log is updated as new issues are identified, and existing issues are resolved.