Project Management Professional (PMP) Exam Practice – Question1656

As you work on your project to update its software training classes to focus on an agile approach, you have a number of key stakeholders. As many students and their managers are requesting these classes, your CEO has taken a special interest in your project
and has asked you to accelerate your schedule to complete it in two months rather than in your planned six months but still have quality offerings. This means as you work to monitor overall project stakeholder relationships, you should______________


A.
Provide notifications to stakeholders about status regularly
B. Ask your stakeholders for regular feedback as you work on your project
C. Provide presentations to each stakeholder group
D. Determine how changes will be monitored and controlled

Correct Answer: D

Explanation:

Explanation:
As you work in managing stakeholder engagement you should review your project management plan. Your CEO has requested a major schedule change; among other things the project management plan is an input to this process as it contains a change
management plan that documents how changes will be monitored and controlled.