Project Management Professional (PMP) Exam Practice – Question1658

A number of items in the stakeholder management plan are similar to those in the communications management plan. An example is______________


A.
Method for updating and refining the plans as the project progresses and develops
B. Stakeholder communication requirements for the current project phase

C. Information to be distributed to stakeholders including language, format, content, and level of detail
D. Time frame and frequency for the distribution of required information to stakeholders

Correct Answer: A

Explanation:

Explanation:
Method for updating and refining the plans as the project progresses and develops The other items listed have specific stakeholder references that, while similar, are not in the communications management plan.