Project Management Professional (PMP) Exam Practice – Question1660

The last step in the stakeholder analysis process is to______________


A.
Determine the organizational culture
B. Assess how stakeholders probably will respond in various situations
C. Determine stakeholder roles, interests, and expectations
D. Evaluate the amount of support each stakeholder could generate

Correct Answer: B

Explanation:

Explanation:
In stakeholder analysis, the last step is to assess how key stakeholders are likely to react or respond to various situations in order to plan how to influence them to enhance their support and mitigate any potential negative impacts.