Project Management Professional (PMP) Exam Practice – Question1663

Work performance information is an output of control stakeholder engagement. It includes a number of items, one of which is______________


A.
Change requests
B. Issue log
C. Documented lessons learned
D. Status of deliverables

Correct Answer: D

Explanation:

Explanation:
Work performance information is performance data collected from various controlling processes that are analyzed and integrated based on relationships among areas. The data are transformed into information, which is correlated and contextualized and provides
a sound foundation for project decisions. The status of deliverables is an example.