In plan stakeholder management, all organizational assets are used as inputs; however, which of the following are of particular importance?


A.
Organization culture and the political climate
B. Practices and habits and templates
C. Lessons learned database and historical information
D. Organization's knowledge management system and policies and procedures

Correct Answer: C

Explanation:

Explanation:
While it is rare that all organizational process assets are used in any process, these are of particular importance as they provide insight on previous stakeholder management plans and their effectiveness. They can be used to plan stakeholder management
activities for the current project.