Project Management Professional (PMP) Exam Practice – Question1670

Assume your stakeholder management plan has been approved. You now are working with your team to promote stakeholder engagement on your project. You explain in a team meeting its benefit is to______________


A.
Clarify and resolve identified issues
B. Meet stakeholder needs and expectations
C. Obtain their continued commitment to the project
D. Increase support and minimize resistance

Correct Answer: D

Explanation:

Explanation:
The other possible answers are activities in the manage stakeholder engagement process. Its benefit is to allow the project manager to increase support and minimize resistance from stakeholders to significantly increase chances for success.