Project Management Professional (PMP) Exam Practice – Question1671

The stakeholder register should not be prepared only one time, but it should be updated regularly especially if______________


A.
The stakeholder is not an active participant
B. The stakeholder is not impacted by the project
C. The stakeholder does not read status updates
D. The stakeholder leads a corporate reorganization

Correct Answer: B

Explanation:

Explanation:
Project document updates are an output to the manage stakeholder engagement process.
These updates involve the stakeholder register. It should be updated as stakeholder information changes, when new stakeholders are identified, or if stakeholders listed in the register are no longer involved in or impacted by the project.