Project Management Professional (PMP) Exam Practice – Question1673

Stakeholder engagement must be controlled on a continuous basis for it to be effective. You realize a number of project documents can be useful for you as a project manager. An example is______________


A.
Technical performance measures
B. Change log
C. Actual costs

D. Start and finish dates of schedule activities

Correct Answer: B

Explanation:

Explanation:
Projects involve change, and most everyone tends to resist it. A change log is useful to review in the control stakeholder engagement process. Other useful documents are the schedule, stakeholder register, issue log, and project communications.