The sponsor is a key project stakeholder because he or she______________
A. Approves or manages the project's product, service, or result
B. Leads the project through initiating until it is formally authorized
C. Is the Chairperson of the project's Governance Board and makes the final go/no-go decision
D. Has a major management role within the administrative area of the business
A. Approves or manages the project's product, service, or result
B. Leads the project through initiating until it is formally authorized
C. Is the Chairperson of the project's Governance Board and makes the final go/no-go decision
D. Has a major management role within the administrative area of the business