Project Management Professional (PMP) Exam Practice – Question1676

Recognizing operations management is different than project management, as the project manager for a new line of electrical tractors to avoid the need to use costly fuel, you realize a best practice is to______________


A.
Document the operational managers' influence either positive or negative in the stakeholder register
B. Offer to include the operational managers in all project phases
C. Recognize that the operational managers are only involved once they have ongoing responsibility for the product, service, or result
D. Realize the operations managers have key responsibilities on the Portfolio Review Board

Correct Answer: B

Explanation:

Explanation:
The needs of operations managers who perform and conduct business operations are important considerations in projects that affect their future work and endeavors. They should be engaged, and their needs identified in the stakeholder register. By considering
them and appropriately including them in all project phases, the project manager can gain insight and avoid unnecessary issues that may arise if their input is overlooked.