Project Management Professional (PMP) Exam Practice – Question1677

Assume you are beginning your project to develop a series of residential condominiums in your city and are identifying possible stakeholders. A key organizational process asset you can review is______________


A.
Organizational culture
B. Organizational standards

C. Lessons learned
D. Local trends

Correct Answer: C

Explanation:

Explanation:
Lessons learned, stakeholder register templates, and stakeholder registers from previous projects are examples of organizational process assets that can influence the identify stakeholders process.