Assume you are managing a project to implement an electronic medical record system in your ophthalmologist's office. You have been working to identify your stakeholders to then make sure everyone is committed to it as some people have been working in this
office for more than 20 years and are comfortable with the manual approach. At this point, you have documented assessment information, which includes______________


A.
Role in the project
B. Whether the stakeholder is a supporter, is neutral, or is resistant
C. Potential influence in the project
D. Organization position

Correct Answer: C

Explanation:

Explanation:
The stakeholder register contains assessment information as a key component. The assessment information includes: major requirements, main expectations, potential influence in the project, and the phase in the project life cycle with the most interest.