Project Management Professional (PMP) Exam Practice – Question1681

Assume you have performed your stakeholder analysis and now are working to enhance it with a stakeholder engagement assessment matrix. Such a matrix shows the stakeholder's current engagement level. These data enable______________


A.
The project manager to prepare the stakeholder management plan
B. The project manager to prepare the stakeholder management strategy
C. The project manager to prepare the stakeholder inventory
D. The project team to expand the stakeholder risk register

Correct Answer: A

Explanation:

Explanation:
The stakeholder engagement assessment matrix shows the stakeholders current engagement in the project, and the project manager and team then can use it to note the desired level of engagement. As a tool and technique in plan stakeholder management, the
project manager then uses it to help prepare the stakeholder management plan.