Project Management Professional (PMP) Exam Practice – Question1684

A supporting input for controlling stakeholder engagement is______________


A.
Budget
B. Project schedule
C. Historical information
D. Number of defects

Correct Answer: B

Explanation:

Explanation:
Project documents are an input to control stakeholder engagement. They originate from initiating, planning, executing, or controlling processes and include the project schedule, stakeholder register, issue log, change log, and project communications.