Project Management Professional (PMP) Exam Practice – Question1685

As a result of the control stakeholder expectations process, you realize even though this process is under way until the closing phase that you have identified the root cause of some issues you have faced in controlling stakeholders expectations. You should

therefore______________


A.
Review them with your Governance Board
B. Revise and reissue your stakeholder management plan
C. Prepare a change request
D. Update the lessons learned documentation

Correct Answer: D

Explanation:

Explanation:
This documentation is an example of an organizational process asset to update as it includes the root cause analysis of issues faced, the reasons certain corrective actions were taken, and other types of lessons learned about stakeholder management.