As a result of the control stakeholder expectations process, you realize even though this process is under way until the closing phase that you have identified the root cause of some issues you have faced in controlling stakeholders expectations. You should
therefore______________
A. Review them with your Governance Board
B. Revise and reissue your stakeholder management plan
C. Prepare a change request
D. Update the lessons learned documentation