Identifying interrelationships and potential overlap between stakeholders is useful to the project manager as he or she works with stakeholders. It should be documented as part of the______________
A. Stakeholder register
B. Stakeholder management strategy
C. Stakeholder management plan
D. Stakeholder engagement assessment matrix
A. Stakeholder register
B. Stakeholder management strategy
C. Stakeholder management plan
D. Stakeholder engagement assessment matrix