Project Management Professional (PMP) Exam Practice – Question1686

Identifying interrelationships and potential overlap between stakeholders is useful to the project manager as he or she works with stakeholders. It should be documented as part of the______________


A.
Stakeholder register
B. Stakeholder management strategy
C. Stakeholder management plan
D. Stakeholder engagement assessment matrix

Correct Answer: C

Explanation:

Explanation:
The stakeholder management plan identifies the management strategies required to effectively engage stakeholders. It includes, among other things, the identified interrelationships and potential overlap between stakeholders. This information is invaluable
especially if some stakeholders are resistant or negative to the project and also in determining the level of frequency of desired interaction and communications requirements.