Project Management Professional (PMP) Exam Practice – Question1688

Table reporting, spreadsheet analysis, and presentations are examples of______________


A.
Project reports as an input to manage stakeholder engagement
B. Work performance information as an output of control stakeholder engagement
C. Tools and techniques used in control stakeholder engagement
D. Updates from the plan stakeholder management process

Correct Answer: C

Explanation:

Explanation:
In control stakeholder engagement, they are examples of distribution formats from information management systems, a tool and technique in this process. Such systems provide a structured tool for the project manager to capture, store, and distribute information
to stakeholders about project cost, schedule progress, and performance. The project manager can use these systems to consolidate reports from several systems and facilitate report distribution.